View the Project on GitHub jaimechu/cmumechatronics2016teamb
Week | Date | Milestone(s) | Task(s) | Presentor |
2 | 18-Jan | Complete design concept proposal
Complete CAD models |
- | |
3 | 25-Jan | Design Concept Proposal (M) | Order parts
Build mock-up design Complete sensors demo |
- |
4 | 1-Feb | Mock-up Demo (M)
Sensors Demo (W) |
Complete motor control lab
Continue working on CAD design |
Sascha (Mock-up Demo)
Nishant (Sensors Demo) |
5 | 8-Feb | Motor Control Demo (W) | Esnure website is updated
Begin sensor testing Consider all physical models |
Jaime |
6 | 15-Feb | System Demo #1 (W)
Website Check (F) |
Continue working on CAD design
Continue sensor testing |
Patricia |
7 | 22-Feb | System Demo #2 (W) | Finalize CAD model and BOM | Andrew |
8 | 29-Feb | Design Presentation (M)
Peer evaluation #1 (Th) |
Begin subsystem prototyping | All |
9 | 7-Mar | Spring Break | ||
10 | 14-Mar | System Demo #3 (W) | Test PCB and finalize frame | Hannah |
11 | 21-Mar | System Demo #4 (W) | Finalize unit and complete sensor assemblies | Andrew |
12 | 28-Mar | System Demo #5 (W)
Website Check #2 (F) |
Integrate mechanical and electrical | Sascha |
13 | 4-Apr | System Demo #6 (W) | Complete final product | Jaime |
14 | 11-Apr | System Demo #7 (W) | Continue testing and tuning of machine and system | Nishant |
15 | 18-Apr | Final System Demo (W) | Prepare for demo | All |
16 | 25-Apr | Final System Demo Encore (W) | Begin writing final report | All |
17 | 2-May | Public Presentation (W)
Final Report (F) |
Complete final report
Complete website content |
All |
18 | 9-May | Website Check #3 (M) | Lab clean up (Tu) | - |
Weekly | Website Update Team Meeting (Sa) | |||
(M)/(Tu)/(W)/(Th)/(F) refers to the day of the week the assignment is due. |